Dunkettle Interchange Update
  • Watermain works are ongoing in the North Esk area of the site. These works will continue for the coming weeks
  • Starter layer construction is continuing in the area adjoining the N25 eastbound on-slip from the Bury’s Bridge Road
  • Site clearance will get underway on site in localised areas next week, with works continuing into week commencing Monday 18th November 2019

The installation of service ducting will get underway by the end of November 2019. This element of works will include roadcrossings which will be undertaken during night-time working hours to ensure no disruption to traffic.