The Dunkettle Interchange Project

Archaeological investigation works have been extended to encompass the entire site. The main construction works are still scheduled to get underway early in 2019, with preparatory works in progress:

  • The planned upgrade to the Silversprings Interchange commenced on the 1st of October with these works aimed at improving the traffic flow for inbound and outbound traffic. These main sections of this work should be completed before the end of the year.
  • The Capacity Improvement Works at the Little Island interchange will go to tender in October, with the aim to appoint a contractor by the end of November 2018. Substantial completion of these works is scheduled for April 2019.
  • To view the before and after photomontages of the Dunkettle Interchange please click here.